How to build a
padel court in Egypt.

Everything to plan before you build: the court models, the space you need, the concrete slab, what goes into the court, the timeline, the warranty and what decides the cost. Written by Sports Developers, the Egyptian company that makes, installs and runs padel courts.

Request a quote Design your court

01 Padel court models

SD makes four court models in its own workshop in Egypt. All of them are built to the international padel court size and can go indoors or outdoors.

ModelPlaying areaWhat makes it different
Super Panoramic10 × 20 mOur flagship. No posts in the corners, glass meets glass, 12 mm tempered glass and the floodlights built into the frame.
Standard10 × 20 mThe classic padel court design, with a framed glass enclosure and steel corner posts.
Single Super Panoramic6 × 20 mThe Super Panoramic as a narrower court for one against one play.
Single Standard6 × 20 mThe Standard as a narrower court for one against one play.

Clubs, schools, compounds and resorts usually choose the Super Panoramic for its open view, which suits tournaments, filmed matches and spectators. See the Super Panoramic in 3D and try your colours.

02 How much space you need

ItemSize
Playing area, doubles court10 × 20 m
Flat space for one courtat least 11 × 21 m
Height inside the court6 m
Clear height for an indoor court8 m
Single court6 × 20 m playing area, less width needed

Planning more than one court? Send us the size of your land and we lay out how many courts fit, with walkways, seating and the rest of the club around them. See the clubs we have built.

03 Foundation and concrete slab

A padel court stands on a level reinforced concrete slab. Getting the slab right matters more than anything else, because a slab out of level shows in the bounce for the life of the court.

  • The frame is anchored to a reinforced ground beam around the court, usually 30 × 30 cm or more.
  • The playing slab is 12 to 15 cm of reinforced concrete.
  • Outdoors the slab gets a slight slope so rain runs off, or porous concrete where the water has nowhere to go.
  • You can build the slab with your own contractor to our levels and dimensions, or we arrange it through our partner contractor.
  • We confirm the right design for your site after the site visit.

04 What goes into an SD court

PartSpecification
Steel frameBox section steel, hot dip galvanised, then powder coated in your colour. Upper beams 8 × 20 cm, support columns 8 × 8 cm, stainless steel fasteners.
Mesh2 × 3 m panels, 4 mm wire.
GlassTempered safety glass, 18 panels of 2 × 3 m, polished and bevelled edges, sealed joints. 12 mm on the Super Panoramic.
Lighting8 LED floodlights of 200 W, IP65 rated for indoor and outdoor use, running cost up to 70% below halogen. Competition lighting on request.
TurfPadel specific curly fibre, 12 mm, with about 3.5 t of silica sand infill. Six colours.
Net and paddingNet and net posts, padding on the door frames and net posts.

Galvanising first and powder coating second is what keeps a court from rusting in Egyptian heat, humidity and sea air. Coastal sites can add an extra protective coating.

05 Colours and branding

  • Four standard steel colours and six turf colours, and any common RAL Classic steel shade on request.
  • Your club or sponsor logo on the padding and the net, custom writing on the net band, and branding on the glass.
  • Extras: ball stop netting, smart cameras and auto ball detection, seating, shade and spectator steps, and turf carried around the court.

Try every steel and turf colour on our court builder, by day and by night.

06 Indoors, outdoors or on a roof

All SD courts work indoors and outdoors. Indoors, plan a clear height of 8 m. On a roof we first check that the structure can carry the court before anything is made.

07 Timeline and payments

Once the concrete slab is ready, manufacturing takes 2 to 3 weeks in our workshop, then installation on site takes 2 to 5 days.

StepWhat happensPayment
1. AgreementSite visit, drawings, colours and a fixed scope.70%
2. ManufacturingSteel cut, galvanised and powder coated in your colour in our workshop.20% when done
3. DeliveryTo your site anywhere in Egypt, or packed for export.
4. InstallationOur own crews install every court in Egypt.
5. HandoverPlayed on, checked and signed off.10% at handover

08 Warranty and maintenance

  • One year warranty from handover on everything except the glass: steel, paint, turf, lights, net and fittings.
  • A court needs regular brushing, the sand spread evenly, clean glass and a check of the joints and bolts.
  • We train your staff at handover and offer maintenance plans and spare parts. We run ten clubs ourselves, so our maintenance team is always working.

09 What decides the cost of a padel court

Every court is quoted for its site. These are the things that change the price:

  • The model: Super Panoramic, Standard or a single court.
  • The number of courts.
  • The concrete slab: already poured, built by your contractor, or arranged by SD.
  • Extras such as competition lighting, branding, ball stop netting, cameras and seating.
  • Delivery outside Egypt and installation supervision abroad.

Send us your details and our court sales team comes back within 24 hours with a quotation for your site.

Request a quote

10 Running the court after it is built

Before you commit, we prepare a return prediction for your site; a well run court typically pays for itself in 1 to 2 years. After handover we can run the court for you: bookings, staff, academy and tournaments, with a monthly report. See how Operate my club works.

11 Courts outside Egypt

We pack courts for export and arrange the freight to your site. Abroad we can send a supervisor to lead your local installation team. SD has built courts in Kenya, in Nairobi and Naivasha.